PROJECT PHOTOS Starting site prep October and November 2002
|
||
|
the future site of SAFE HARBOR dome
using bobcat to move dirt
looking northeast
starting the deliveries
looking southeast
adding more layers of compacted dirt
bringing in the big loader - 60,000 lbs
bringing height up to 22.12'
pile of old orange trees from grove area
showing new higher grade
looking toward office
grading new gravel on drive |
We decided to place the dome on the 1 acre of residential property that is west of the 2 acres of limited commercial property that our current house is on. There are 33 orange trees that were part of a small grove that Billy's grandparents grew.
starting the site prep
starting the circle of dirt
raising the finished floor height
keeping up with the trucks
looking due south
looking southwest
Billy talking with Chester Smith
grading front entrance
looking toward old shed at back
looking due east
grading front lawn
looking due north toward street |